    How to import Planner tasks as Key dates to PPM Express

    In this article, we will review how to import Key Dates from the Planner project to the PPM Express project.

      Planner connection is not available for Core plan. 


    If you have added Planner connection to PPM Express and linked PPM Express project to Planner plan, it is possible to import tasks from Planner plan to PPM Express project as Key Dates. 

    Please note: Only those tasks that have 'Due date' field filled in can be imported as Key Dates from Planner to PPM Express.

    If Planner task was imported to PPM Express as Key Date and after this Due date was deleted from Planner task in Planner, this Key Date will be automatically deleted from PPM Express Key Dates after data synchronization. 


    Please note: Only users who have permissions to edit the PPM Express project can import Key Dates. 

    If the Planner connection is not added and the Planner plan is not linked to the PPM Express project yet, then to be able to import Key Dates, it is required to have Manage Integrations and Edit Project permissions

    Importing Planner tasks as Key Dates

    To import tasks from Planner plan as Key Dates to PPM Express project perform the following:

    1. Open PPM Express project that is linked to the Planner plan and where you would like to import Key Dates. 

    2. Navigate to the Key Dates section of the project and select the Import Key Date option. 

    3. In the Import Key Date window, it is possible to search for the required Planner task by Name, Type or ID. Or you can just click in the search window and 10 Planner tasks will become available for selection. As you select to import them as Key dates, the next tasks will become available in the list. 

    4. To select the tasks you would like to import just click on it and it will be added to the list of the selected items. When you are ready with the selection click Confirm to import the selected tasks to PPM Express as Key Dates. 

    You can delete the unnecessary items from this list or open them in Planner. 

    5. As you click Confirm the selected items will be added to the Key Dates section. 

    The statuses and the names for the imported Key Dates are imported from Planner and cannot be changed within PPM Express. If there are any changes to the tasks in Planner, they will be applied to PPM Express Key Dates after data synchronization automatically. Only internal PPM Express fields can be edited for the imported Key Dates. 

    Statuses will be set according to the tasks due date, taking into account the current date: 

    • 'Done' will be set for the tasks that have 'Completed' status in Planner. 
    • 'Critical' will be set for the tasks that are late >10 days and not completed. 
    • 'At risk' will be set for the tasks that are late <=10 days and not completed. 
    • 'On Track' will be set for all other cases, for the tasks where the date field is greater than the current date (today).

    The tasks imported as key dates can be opened in Planner from PPM Express Key dates section directly by clicking on the Planner icon next to each Key date. 


    Deleting Planner tasks imported as Key Dates

    To delete the imported Key Dates perform the following:

    1. Open PPM Express project where Planner tasks were imported as Key Dates. 

    2. Select the Key Dates you need to delete from the list. 

    3. Click the Delete Key Date button. 

    4. Confirm that you would like to remove the Key Dates. The selected Key Dates will be deleted at once. 

    Please note: After data synchronization, the deleted Key Dates will not appear again in the Key Dates section automatically. If you need to add the deleted items again, it will be needed to import them following the steps described in the 'Importing Planner tasks as Key Dates' section of this article.

    If PPM Express project is linked to Planner and Azure DevOps and the Key dates are imported from both systems, then in the Import Key dates window it will be possible to switch between these systems. Switching between the systems you can review and manage the list of imported key dates for each system separately.